Westbound detour planned for Wednesday and Thursday

State College, PA – The Pennsylvania Department of Transportation (PennDOT) is issuing a mid-November update for its Route 322/Potters Mills Gap project in southeast Centre County. Up-to-date information can also be found on the PMG Project page at www.penndot.gov/pottersmillsgap.

Drivers can expect the following November 18—22:

  • Westbound traffic will be detoured on Wednesday, November 20 and Thursday, November 21 between the hours of 9:00 A.M. and 3:00 P.M. The westbound detour uses Route 144 and Route 45. This detour is necessary so that crews can move barrier and install pavement markings on the western end of the project. During this time, eastbound traffic will move through the project normally, using existing Route 322.
  • Work will continue off the roadway and drivers should be alert for construction vehicles entering and exiting Route 322 through the Potters Mills area. Flaggers in the roadway may be aiding construction vehicle movements. Do not follow construction equipment into the work area.
  • Motorists are reminded that eastbound traffic now uses the new local access road (Route 2015) east of Potters Mills for one mile before using a crossover to return to existing Route 322. This traffic pattern will be in place for the duration of the project.
  • Motorists are reminded that westbound traffic no longer uses the crossover and is now routed onto the new local access road (Route 2015) east of the intersection of Routes 322 and 144. This traffic pattern will be in place for the duration of the project.
  • There is a 12-foot width restriction on the western end of the project between Route 144 and Mountain Back Road. This restriction will be in effect until the fall of 2020.
  • There is a 14-foot width restriction on the eastern end of the project between Sand Mountain Road and Route 144. This restriction will be in effect until the fall of 2020.

This is the third and final phase of a construction project dating back to 2015. Phase One of the project constructed the new bridge at Sand Mountain Road. Phase Two created the new local interchange on Route 322 at Sand Mountain Road. The goal of Phase Three is to reconstruct Route 322 from Sand Mountain Road to Potters Mills – including a new Route 322/Route 144 intersection. The completed project will alleviate congestion and allow traffic to move more safely and efficiently from the Centre/Mifflin County line to Potters Mills.

Glenn O. Hawbaker, Inc. of State College is the contractor on this $82 million project.  

Motorists are encouraged to “Know Before They Go” by checking conditions on more than 40,000 roadway miles by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information and access to more than 950 traffic cameras.

511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1, or by following regional Twitter alerts accessible on the 511PA website.

Subscribe to PennDOT news in Cameron, Centre, Clearfield, Clinton, Elk, Juniata, McKean, Mifflin, and Potter counties at www.penndot.gov/District2.

For regional updates on Twitter, follow www.twitter.com\511PAStateCOLL

MEDIA CONTACT:  Marla Fannin(814) 765-0423, Timothy Nebgen (814) 765-0598